Oracle 1z0-1057-24 Practice Exam - 128 Unique Questions
Latest Questions 1z0-1057-24 Guide to Prepare Free Practice Tests
NEW QUESTION # 71
Your client organization has recently undergone a restructuring exercise that has resulted in the creation of new jobs. The Resource Breakdown Structure (RBS) was previously created with existing jobs, and now the new jobs have been added to the existing Resource Breakdown Structure.
Identify the correct statement about the RBS and new resources. (Choose the best answer.)
- A. If the "Allow resource changes at project level" option is enabled for the RBS, the new resources added at project level are automatically reflected in the RBS.
- B. If the "Allow resource changes at project level" option is set to No, the new resources and resource formats that are added to a Planning Resource Breakdown Structure for one project are not available for other projects.
- C. If the "Allow resource changes at project level" option is set toNofor the RBS, then the resources added to the Planning Resource Breakdown Structure are automatically available for use on the projects.
- D. If the "Allow resource changes at project level" option is set to Yes for the RBS, the new resources are available automatically at project level.
Answer: C
Explanation:
Ref:https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19a/fapfm/implementing-project- financial-management-applications.html#FAPFM969761 Topic - Entering Planning Resource Breakdown Structure Details
* ClickNavigator > Setup and Maintenance, and search for theManage Planning and Billing Resource Breakdown Structurestask.
* Click theManage Planning and Billing Resource Breakdown Structureslink.
Use the Manage Planning and Billing Resource Breakdown Structures page to create new planning resource breakdown structures and to review existing planning and billing resource breakdown structures.
* Click theCreateicon in the Planning Resource Breakdown Structures section.
* Use the Create Planning Resource Breakdown Structure: Basic Information page to provide basic resource breakdown structure information including the name, active dates, and project unit.
* Enter a planning resource breakdown structure name and select a date from which the resource breakdown structure is available for use.
* Optionally, provide a description and a date to which the planning resource breakdown structure is available for use.
* Select a project unit. Only projects created for the selected project unit can use this planning resource breakdown structure.
* If you want to allow project managers to add planning resources at the project level, then select the Allow resource changes at project levelcheck box.
Tip:Changes at the project level don't move back to the parent planning resource breakdown structure.
Deselect this option to ensure all project using the planning resource breakdown structure use the same resources.
* Optionally, select aJob Setas a source of jobs for creating planning resources on your planning resource breakdown structure.
* ClickSave.
NEW QUESTION # 72
In a Project Draft Invoice preview, quantity (hours) and unit price (bill rate) are shown as fields on the invoice. Quantity and unit price are then used to calculate the line total, then the total price of the invoice.
After the invoice is transferred or created in Receivables, the invoice detail has a quantity of 1, and a unit price equal to the line total. The detailed Unit Price/Quantity does not come through on the Receivables invoice.
Identify the correct statement about details in the receivables invoice. (Choose the best answer.)
- A. The project sends only the invoice header and invoice line description to Receivables, not the invoice distributions.
- B. The project sends only the invoice header to Receivables, not the invoice line description and distributions.
- C. The project sends the invoice header, invoice line description, and the invoice distributions to Receivables.
- D. The project sends the invoice line description and the invoice distributions to Receivables, but not the invoice header.
Answer: A
Explanation:
When a project invoice is transferred or created in Receivables, the project sends only the invoice header and invoice line description to Receivables, not the invoice distributions. The invoice distributions contain the detailed information such as quantity, unit price, and line total. Therefore, the Receivables invoice does not show these details, but only shows a quantity of 1 and a unit price equal to the line total.Reference:
https://docs.oracle.com/en/cloud/saas/project-portfolio-management/20c/oapfm/manage-project-invoices.
html#OAPFM2355931
NEW QUESTION # 73
Which product offering simplifies the planning, budgeting, and forecasting capabilities as part of Project Management Cloud?
- A. Project Control
- B. Project Billing
- C. Enterprise Contract Management
- D. Project Costing
Answer: A
Explanation:
Project Control is the product offering that simplifies the planning, budgeting, and forecasting capabilities as part of Project Management Cloud. Project Control allows you to create and manage project plans, budgets, and forecasts using various methods andsources. You can also monitor and control project performance and variances using dashboards and reports. Reference:https://docs.oracle.com/en/cloud/saas/project-portfolio- management/20c/oapfm/manage-project-plans.html#OAPFM2356061
NEW QUESTION # 74
Your customer wants to generate accounting based on project information associated with the transaction for all subledger transactions. Identify three subledger applications for which the project source is available for deriving accounts when configuring subledger accounting. (Choose three.)
- A. Payables
- B. Receipt Accounting
- C. Purchasing
- D. Fixed Asset
Answer: A,B,C
Explanation:
Ref:https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19b/oapfm/project-costing- configuration-define-project-costing-integrations.html#OAPFM3094605 Topic - Deriving Projects-Related Accounts
NEW QUESTION # 75
Identify two attributes for which you can enter budgets that will be considered for Budgetary Controls in Project Portfolio Management. (Choose two.)
- A. expenditure item
- B. resource
- C. project classification
- D. project plan type
- E. project
Answer: B,E
Explanation:
Reference: https://docs.oracle.com/cloud/latest/projectcs_gs/OAPJF/OAPJF1121937.htm#OAPJF1121937
NEW QUESTION # 76
You cannot generate invoices for a project expenditure item. After running the Generate Invoices program for a billable expenditure item and active contract, the process completessuccessfully but without any billing, and does not provide any error logs.
The program's processing summary is as follows:
Billing Event Errors 0
Ineligible Contracts 0
Successfully Billing Events Created 0
Ineligible Contract Lines 0
Billing Transaction Exception Errors 0
Ineligible Bill Plans 0
Billing Transaction Exception Warnings 0
Ineligible Associated Projects 0
Successful Billing Transactions 0
Ineligible Expenditure Items 0
Draft Invoice Exception Errors 0
Ineligible Events 0
Draft Invoice Exception Warnings 0
Successful Draft Invoices 0
What was the invoice method classification set to that caused this behavior? (Choose the best answer.)
- A. Amount Based
- B. Percent Complete
- C. Rate Based
- D. As Incurred
Answer: A
Explanation:
Reference: https://docs.oracle.com/cd/E51367_01/projectop_gs/OAPJB/F1087458AN139C2.htm Topic - Invoice and Revenue Rates: How They Are Determined Oracle Fusion Project Billing uses bill rates, burdening, and transfer price schedules to derive standard bill rates, multipliers, markups, and bases for calculating potential revenue when the revenue method classification on a revenue plan is as billed, as incurred, or rate based. Similarly,bill rates derive invoice amounts when theinvoice method classification on a bill plan is rate based.
NEW QUESTION # 77
Using Oracle Time and Labor, your client wants to put in a validation process that allows only a certain number of maximum hours an employee can charge in a day, and a minimum of hours he or she can report in a week.
What feature would you use to meet this requirement? (Choose the best answer.)
- A. time audit rules
- B. time entry rules
- C. time calculation rules
- D. project time validation rules
Answer: B
Explanation:
To put in a validation process that allows only a certain number of maximum hours an employee can charge in a day, and a minimum of hours he or she can report in a week, you need to use time entry rules. Time entry rules allow you to define the conditions and actions for validating time entries based on various attributes such as hours, dates, projects, tasks, etc. You can also specify the error messages and severity levels for the time entry rules. Reference:https://docs.oracle.com/en/cloud/saas/project-portfolio-management/20c/oapfm
/manage-project-time-and-labor.html#OAPFM2355991
NEW QUESTION # 78
You are implementing Project Portfolio Management (PPM) for a professional services firm. The firm rents multiple buildings for its operations. At the end of each month, they review the rent expense for the month and want to allocate the rental cost to all the projects and tasks that are executed by associates in each of the buildings. The source amounts must be proportionally allocated to the tasks based on the raw costs of the tasks from the previous month. Considering that all these costs are in General Ledger, what three allocation setups should you complete in PPM? (Choose three.)
- A. Define allocation basis by using Actual Amounts with aperiod-to-date amount class.
- B. Allocate rental costs once each accounting period by using the "spread evenly" allocation method.
- C. Allocate rental costs once each accounting period by using the"full" allocation method.
- D. Define allocation basis by using Actual Amounts with a project-to-date amount class.
- E. Allocate to all eligible tasks and prorate the allocation by thetotal actual raw costaccrued for each task during theprevious accounting period.
Answer: A,C,E
Explanation:
To allocate the rental cost to the projects and tasks based on the raw costs of the tasks from the previous month, you need to do the following:
* Allocate rental costs once each accounting period by using the "full" allocation method. This method allocates the entire source amount to the target tasks in one run.
* Allocate to all eligible tasks and prorate the allocation by the total actual raw cost accrued for each task during the previous accounting period. This ensures that the source amount is proportionally allocated to the tasks based on their relative raw costs.
* Define allocation basis by using Actual Amounts with a period-to-date amount class. This allows you to use the actual raw costs of the tasks as the basis for allocation and to use the amounts from the previous accounting period. Reference: https://docs.oracle.com/en/cloud/saas/project-portfolio-management/20c
/oapfm/manage-project-costs.html#OAPFM2355951
NEW QUESTION # 79
You have a small project for a period of five months. Your budget amount for each month is spread evenly and is $1000 per month. The first month actual expense is $800 and there is a commitment for $600. Now you generate a forecast at the beginning of the second month. Identify the monthly Estimate-To-Complete (ETC) amount that the application would calculate for the remaining four periods, when the ETC generation method includes commitments. (Choose the best answer.)
- A. 0
- B. 1
- C. 2
- D. 3
Answer: A
Explanation:
Budget 5,000Actuals 800Commitment 600
ETC = Budget - Actuals - Commitment
ETC = 5,000-800-600 = 3,600 Budget available for next 4 months = 3,600/4 = 900/month
NEW QUESTION # 80
Identify three purposes for which the project resource search index is used. (Choose three.)
- A. Calculate Resource Qualification Scores
- B. Provide absence details for resources
- C. Display resource details
- D. Calculate Resources Availability Scores
- E. Filter counts while you search for resources
Answer: A,C,E
Explanation:
The project resource search index is used to store and retrieve information about project resources such as their availability, qualifications, preferences, etc. The project resource search index is used for three purposes:
* Display resource details: The project resource search index provides the resource details such as name, email, job title, organization, etc. that are displayed on the resource search page.
* Filter counts while you search for resources: The project resource search index provides the filter counts that show how many resources match each filter criterion on the resource search page.
* Calculate Resource Qualification Scores: The project resource search index provides the qualification information such as skills, certifications, languages, etc. that are used to calculate the Resource Qualification Scores for each resource based on their match with the resource request. The project resource search index does not provide absence details for resources or calculate Resource Availability Scores. These are provided by other components such as Oracle Fusion Absence Management and Oracle Fusion Human Capital Management. Reference: https://docs.oracle.com/en/cloud/saas/project- portfolio-management/20c/oapfm/manage-project-resources.html#OAPFM2356181
NEW QUESTION # 81
Your business user has created a purchase order (PO) that has the following attributes:
Accrue at Receipt = Yes
Matching Option = 2 way
Receipt Close Tolerance = 100%
After approval, the PO is closed for receiving without creating a receipt. An AP invoice is created by matching to the PO. The user now runs Create Accounting for Receiving Transactions and then the "Import and Process Cost transactions" ESS (Enterprise Scheduler Service) job using the Transaction Source parameter as "Oracle Payables". The user notices that there is no cost transferred to the projects. Identify two reasons for this problem. (Choose two.)
- A. When you have an AP invoice that is matched against a PO with Accrue at Receipt set to YES, cost is transferred to projects by Cost Management and not by Payables.
- B. When you have an AP invoice that is matched against a PO with Accrue at Receipt set to Yes, cost is transferred to project by payables.
- C. When you have an AP invoice that is matched against a PO with Accrue at Receipt set to Yes, cost is transferred to projects only if there are accounted receipt lines.
- D. When you have an AP invoice that is matched against a PO with Accrue at Receipt set to NO, cost is transferred to projects by receipt accounting.
Answer: A,C
Explanation:
When the Accrue at Receipt option is set to Yes on a PO, the cost of the items or services is accrued when they are received, not when they are invoiced. Therefore, the cost is transferred to projects by Cost Management and not by Payables. However, if the PO is closed for receiving without creating a receipt, there will be no accounted receipt lines and no cost will be transferred to projects. To transfer the cost to projects, you need to either create a receipt or reopen the PO for receiving.Reference:https://docs.oracle.com/en/cloud
/saas/project-portfolio-management/20c/oapfm/manage-project-costs.html#OAPFM2355855
NEW QUESTION # 82
As you go through the first-quarter close for your customer, you notice that the burden amounts calculated do not seem to be right. Based on the calculations, you notice that the amounts calculated are not considering the burden schedule override at a task level, which was done during the second month of the quarter.
What is the reason for this problem?
- A. Only new expenditure items charged to the task use the new burden schedule; expenditure items processed earlier can be manually marked for reprocessing.
- B. Only new expenditure items charged to the task use the new burden schedule; expenditure items processed earlier cannot be reprocessed.
- C. You can enable automatic reprocessing of expenditure items processed before the burden schedule change.
- D. All expenditure items charged to the task use the new burden schedule.
Answer: A
Explanation:
Reference: https://docs.oracle.com/cloud/r13_update17b/projectcs_gs/OAPJC/OAPJC1071490.
htm#OAPJC1071482
NEW QUESTION # 83
Your customer has a requirement to import and process third-party transactions that are "costed" and
"accounted".
Which configuration option needs to be set satisfy the requirement? (Choose the best answer.)
- A. Import Options
- B. Transaction Source Options
- C. Document Entry Options
- D. Document Options
Answer: B
Explanation:
Reference: https://docs.oracle.com/cd/E51367_01/projectop_gs/OAPJC/F1071488AN1004C.htm To import and process third-party transactions that are costed and accounted, you need to set the Transaction Source Options for the transaction source that you use to import the transactions. The Transaction Source Options allow you to specify whether the transactions are costed and accounted by the source system or by Oracle Fusion Cost Management. You can also specify whether to validate and transfer costs and accounting entries to projects and general ledger.Reference:https://docs.oracle.com/en/cloud/saas/project-portfolio- management/20c/oapfm/manage-project-costs.html#OAPFM2355941
NEW QUESTION # 84
Identify theattribute of a project typethatdetermines if expenditure items are billable, and theamount type to be used as the basisfor transfer pricing. (Choose the best answer.)
- A. event type
- B. cost type
- C. work type
- D. expenditure type
Answer: C
Explanation:
Reference https://docs.oracle.com/cloud/latest/projectcs_gs/OAPFM/OAPFM1125361.htm#OAPFM1125277 (what's a work type?) In billing, you can use work types to classify work for the following purposes:
* To determine the default billable status of expenditure items.
* To classify cross-charge amounts into cost and revenue for cross-charge transactions.
Tip:To use work types to determine whether an expenditure item is billable you must set the profile option Work Type Derived for Expenditure Item toYes.
When you create or import expenditure items, the default work type is inherited from the associated task.
Tasks, in turn, inherit work type values from parent tasks and ultimately from the project.Project types determine the default work type value for projects and project templates.
NEW QUESTION # 85
You havedefined two expenditure types, but they are not available for selection when you enter an expenditure batch. Identify the reason for this problem. (Choose the best answer.)
- A. The two expenditure types are not assigned to the reference data set that is assigned to the project- owning organization in which the transaction is performed.
- B. The two expenditure types are not assigned to the reference data set that is assigned to the project expenditure organization in which the transaction is performed.
- C. The two expenditure types are not assigned to the reference data set that is assigned to theproject unit in which the transaction is performed.
- D. The two expenditure types are not assigned to the reference data set that is assigned to the business unit in which the transaction is performed.
Answer: C
Explanation:
Ref: Implementing-Project-Financial-Management-and-Grants-Management.pdf (19A Part # F11256-01) Chapter 3 - Define Project Organizations Topic - Set Assignments and Project Data - How They Work Together (Page 29) Business Unit as Set Determinant Business units enable you to control and report on financial transactions, usually for specific geographical entities within the enterprise. For project management purposes, assign the Project Accounting business function to the business unit.
Business unit is a set determinant for the project-related reference data objects described in the following table.
Ref Data Object
Entities
Project Accounting Definition
Project Types
Project Rates
Project rate schedules
Project Unit as Set Determinant
Use project units to enforce consistent project management practices across your enterprise. Project unit is a set determinant for the reference data objects described in the following table.
Ref Data Object
Entities
Project Definition
Class codes, financial plan types, project plan types and project roles Project Transaction Types Expenditure types and work types You can only select class codes, plan types, roles, expenditure types and work types that are assigned to the same set as the project unit. To enable expenditure types and work typesfor use on projects owned by a project unit, assign the set associated with the Project Transaction Types reference data object to those entities
NEW QUESTION # 86
......