[Sep-2025] AACE-PSP Exam Dumps Pass with Updated 2025 Planning & Scheduling Professional (PSP) Exam [Q83-Q104]

Share

[Sep-2025] AACE-PSP Exam Dumps Pass with Updated 2025 Planning & Scheduling Professional (PSP) Exam

Free AACE-PSP Exam Dumps to Pass Exam Easily

NEW QUESTION # 83
What was the original planned duration for Activity A through Activity G?

  • A. 24.
  • B. 25.
  • C. 28.
  • D. 26.

Answer: C


NEW QUESTION # 84
What is the primary difference between the arrow diagramming method (ADM) and the precedence diagramming method (PDM)?

  • A. PDM is a bar chart with network logic, while ADM is a pure logic network.
  • B. ADM is limited to finish-to-start logic relationships, while PDM is not.
  • C. ADM uses arrows, while PDM uses boxes.
  • D. ADM is manual CPM calculations, while PDM is computerized.

Answer: B


NEW QUESTION # 85
What day would Activity C complete if the duration of Activity A was reduced by five days?

  • A. 0
  • B. 1
  • C. 2
  • D. 3

Answer: C


NEW QUESTION # 86
Activity durations are normally estimated in an intuitive and subjective way. All of the following will improve duration accuracy EXCEPT

  • A. Look at each activity independently and don't follow specific logic paths when assigning activity durations.
  • B. Use gross building square footages. The pluses and minuses all average out.
  • C. Use the people responsible for performing the work as a resource to assign activity durations.
  • D. Divide activities into smaller activities. This will increase activity detail and duration estimate accuracy.

Answer: B


NEW QUESTION # 87
Using the "crashed" schedule, if you start Activity 2002 on August 12, 2001, what is the finish date for Activity 2002?

  • A. 09-18-01.
  • B. 09-28-01.
  • C. 09-15-01.
  • D. 09-08-01.

Answer: D


NEW QUESTION # 88
How many workdays occur from the start of the Product Testing to the Product Available milestone?

  • A. 0
  • B. 1
  • C. 2
  • D. 3

Answer: B


NEW QUESTION # 89
Which of the following phases does NOT describe the commonly accepted construction life cycle?

  • A. Installation phase.
  • B. Planning and design phase.
  • C. Claims and disputes phase.
  • D. Turnover and start-up phase.

Answer: B


NEW QUESTION # 90
The amount of time that an activity can be delayed from its early start date without delaying project completion is called

  • A. Interfering float.
  • B. Free float.
  • C. Negative float.
  • D. Total float.

Answer: D


NEW QUESTION # 91
What is the remaining work duration of Active D?

  • A. 4.
  • B. 8.
  • C. 3.
  • D. 0

Answer: A


NEW QUESTION # 92
Using the "normal" schedule, and assuming you are billing on the last day of the month for previous month and for appropriate partial months, how many invoices will you have for this project?

  • A. 37.
  • B. 40.
  • C. 42.
  • D. 36.

Answer: D


NEW QUESTION # 93
Using the normal schedule and excluding general conditions, which activities are NOT on the critical path?

  • A. 5001,7001.8001,9001,9004,9005
  • B. 7001, 8001, 9001. 9003. 9004. 10002
  • C. 6001, 8001, 9001. 9002, 9004. 9005
  • D. 2003,8001.9001.9002,9005,10001

Answer: C


NEW QUESTION # 94
Assuming conventional finish-to-start relationships, to calculate a schedule retaining the existing logic means that

  • A. It is calculated using the original logic.
  • B. There is no such thing.
  • C. An out-of-sequence activity cannot resume until all predecessors are finished.
  • D. It is calculated using logic reflecting out-of-sequence progress.

Answer: A


NEW QUESTION # 95
What activities are concurrent to Activity 2001 in the "normal" schedule?

  • A. 7001.
  • B. 1001.
  • C. 2003.
  • D. 1000.

Answer: A


NEW QUESTION # 96
Why does activity 11001 not show successor activities?

  • A. It is the final activity for the required work for the project
  • B. The early finish and late finish are circular
  • C. It is the penultimate work required for the project
  • D. The scheduler forgot to add the successor activities

Answer: A


NEW QUESTION # 97
Due to a testing delay, release of the product for manufacture is delayed by 5 workdays and the product manual misses its print window at the printer. If the printer is delayed by 10 workdays, what is the delay to produce release?

  • A. 5 days.
  • B. 15 days.
  • C. 0 days.
  • D. 10 days.

Answer: A


NEW QUESTION # 98
Is activity 7001 pictured correctly in the precedence diagram?

  • A. No, the total float is not shown correctly.
  • B. Yes, except the early finish date is not shown.
  • C. Yes, the duration is 48 days.
  • D. No, the start-to-start and finish-to-finish relationships are backwards.

Answer: C


NEW QUESTION # 99
Why does activity 11001 not show successor activities?

  • A. It is the final activity for the required work for the project
  • B. The early finish and late finish are circular
  • C. It is the penultimate work required for the project
  • D. The scheduler forgot to add the successor activities

Answer: A


NEW QUESTION # 100
Activity C is a

  • A. 1-day activity.
  • B. Contentious activity.
  • C. Milestone.
  • D. Continuous activity.

Answer: C


NEW QUESTION # 101
In the "normal" schedule, excluding Activity 1000, what activity(s) are concurrent with Activity 3001?

  • A. 2003 and 7001.
  • B. 2004.
  • C. 4001 and 5001.
  • D. 4001, 5001 and 6001.

Answer: C


NEW QUESTION # 102
Project delays are best analyzed

  • A. Late in the project.
  • B. Contemporaneously with the delay.
  • C. After either the contractor or the owner acknowledges ^responsibility for the delay.
  • D. By an expert after the project is finished when complete records are available and the impact is known.

Answer: D


NEW QUESTION # 103
How much Total Float does drafting the product manual have?

  • A. 10 workdays.
  • B. 0 workdays.
  • C. 15 workdays.
  • D. 5 workdays.

Answer: A


NEW QUESTION # 104
......