SAP Certified Application Associate C_TS422_1909 Real Exam Questions and Answers FREE Updated on Oct 22, 2022
C_TS422_1909 Ultimate Study Guide - Prep4sures
NEW QUESTION 11
The settings for MRP can be maintained at different levels. If settings have been maintained in different places, in which sequence does the system search for the MRP settings?
Please choose the correct answer.
Response:
- A. Plant Settings -> MRP Group -> Material Master
- B. Material Master -> Plant Settings -> MRP Group
- C. MRP Group -> Material Master -> Plant Settings
- D. Material Master -> MRP Group -> Plant Settings
Answer: D
NEW QUESTION 12
Which document is skipped when SAP EWM is embedded in SAP S/4HANA?
Please choose the correct answer.
Response:
- A. Warehouse order
- B. Outbound delivery request
- C. Outbound delivery order
- D. Warehouse task
Answer: B
NEW QUESTION 13
To ensure that the warehouse operator only stages large components in the exact required quality for each production order, which warehouse material staging method would you recommend?
Please choose the correct answer.
Response:
- A. Release order parts
- B. Pick parts
- C. Crate parts
- D. Kanban
Answer: B
NEW QUESTION 14
What are the possible results of a production planning run in Advanced Planning (PP/OS)? Note: There are 3 correct answers to this question.
- A. Stock transport order
- B. Scheduling agreement schedule line
- C. Production order
- D. Planned order
- E. Purchase requisition
Answer: B,D,E
NEW QUESTION 15
What are some uses for the low-level code assigned to each material? Note: There are 2 correct answers to this question.
- A. It is used by ATP to determine the priority of alternative components.
- B. It is used in MRP to determine the sequence in which materials are planned.
- C. It is used by engineering to identify sub items in an engineering bill of material(BOM).
- D. It is used by product costing to determine how costs are rolled up.
Answer: B,D
NEW QUESTION 16
Which of the following elements does MRP take into account during net requirement calculation? Note: There are 2 correct answers to this question.
- A. Purchase orders
- B. Lot size
- C. Safety stock
- D. Maximum stock level
Answer: B,C
NEW QUESTION 17
What is the correct sequence of the following Activate methodology phases?
Please choose the correct answer.
Response:
- A. Prepare, Realize, Iterate, Continuous Improvement
- B. Prepare, Validate, Test, Go-Live
- C. Prepare, Explore, Realize, Deploy
- D. Validate, Realize, Test , Deploy
Answer: C
NEW QUESTION 18
How can you limit the validity of a bill of material (BOM)? Note: There are 2 correct answers to this question.
- A. By period
- B. By plant
- C. By material type
- D. By industry
Answer: A,B
NEW QUESTION 19
You have maintained the parameters for simple discontinuation the material master of a component. Which business process will be affected if the available stock is zero and the discontinuation date is in the past?
- A. Material requirements planning
- B. Production order release
- C. Kanban
- D. Back flushing
Answer: A
NEW QUESTION 20
In which of the following master data objects can you define the production order default storage location for a material component?
There are 2 correct answers to this question.
Response:
- A. Work center, in the production supply area
- B. Routing, in the component allocation
- C. BOM, in the item for the material
- D. Material master of the finished product
Answer: A,C
NEW QUESTION 21
How would you define pegging in the context of Advanced Planning?
- A. An evaluation to verify if there are overstock situations in the balance between receipt and issue elements after the production planning run.
- B. An evaluation that is ordered according to the bill-of-material structure of all related products and represents the relationship between the receipt and the issue elements.
- C. An evaluation to verify if there are mater al or capacity shortages in the network after the production planning run.
- D. An evaluation that is ordered according to the network structure of all related products and represents the coverage of issue elements with receipt elements.
Answer: B
NEW QUESTION 22
What is the purpose of collective orders?
- A. To manage production orders for an entire finished product on multiple levels
- B. To post any component withdrawals single back flush with order confirmation
- C. To post production costs on a cost collector instead of the production order
- D. To combine order management of co-products and by-products with the main product
Answer: A
NEW QUESTION 23
Which material-specific information can be transferred to a transportation lane in PP/DS?
There are 3 correct answers to this question.
Response:
- A. Special procurement keys
- B. Purchasing info records
- C. Outline agreement
- D. Quota arrangements
- E. Production versions
Answer: A,B,C
NEW QUESTION 24
How can you set up the supply source for the SAP Kanban process? Note: There are 3 correct answers to this question.
- A. Using stock transfer reservations for stock transfer
- B. Using run schedule quantities for in-house production
- C. Using purchasing costs for automated source prioritization
- D. Using quotations for internal and external procurement
- E. Using purchase orders for external procurement
Answer: A,B,E
NEW QUESTION 25
You want to schedule an operation finitely, without moving other operations. Which scheduling strategy do you select?
- A. Scheduling working time only
- B. Squeezing
- C. Insert operation
- D. Find Slot
Answer: D
NEW QUESTION 26
When the goods receipt for a finished product is posted during confirmation on a manufacturing environment, which of the following actions are also performed by default?
There are 2 correct answers to this question.
Response:
- A. Reduction of the capacity requirements
- B. Staging of components for the next order in the sequence
- C. Posting of production costs to cost collector
- D. Archiving of backflush documents
Answer: C,D
NEW QUESTION 27
A warehouse manager likes to streamline the goods receipt (GR) process for production orders. Where can you enable the automatic GR?
There are 2 correct answers to this question.
Response:
- A. Scheduling margin key
- B. Confirmation profile
- C. Production scheduling profile
- D. Operation control key
Answer: C,D
NEW QUESTION 28
You need to model goods receipt processing time in Detailed Scheduling. Which modelling options do you have? Note: There are 2 correct answers to this question.
- A. Model a resource inbound in the location master.
- B. Model a separate resource in the production data structure.
- C. Model a transportation resource in the location master.
- D. Model a handling resource in the location master and goods receipt time in the mater all master.
Answer: C,D
NEW QUESTION 29
In the Manage Shortage view of the new SAP Fiori app "Monitor Material Coverage", what do the stars indicate?
Please choose the correct answer.
Response:
- A. The presence of production orders
- B. The viability of the proposed solution
- C. The presence of firmed planned orders
Visit us athttp://examcertify.com/C_TS422_1909.html - D. The priority of the proposed solution
Answer: B
NEW QUESTION 30
If the stock level drops below the reorder stock in reorder point planning, what is the system logic to trigger procurement?
- A. Fill up to the reorder stock level
- B. Fill up to the maximum stock level
- C. Fill up to the safety stock level
- D. Fill up based on the lot size procedure
Answer: D
NEW QUESTION 31
Which functional capabilities does the Detailed Scheduling Board have?
There are 2 correct answers to this question.
Response:
- A. Undo for drag & Drop planning activities
- B. Change sales order quantities
- C. Change planned order quantities
- D. Enter time-ticket confirmation for production orders
Answer: A,C
NEW QUESTION 32
Your production planners must execute planning only for specific resources. How can you achieve this in Advanced Planning (PP"/OS)?
- A. Use a propagation range.
- B. Use a planning group.
- C. Use a heuristic.
- D. Use a resource group.
Answer: C
NEW QUESTION 33
......
SAP C_TS422_1909 Certification Exam Topics:
| Topic Areas | Topic Details, Courses, Books |
|---|---|
| Production Orders in SAP S/4HANA > 12% | Determine BOM item category, describe order status management and set user statuses, configure availability check for components, trigger routing selection, set up an order type, apply material staging and confirmation. |
| Introduction to SAP S/4HANA Supply Chain Planning < 8% | Outline both motivation and background of SAP S/4HANA, describe its main components, the lines of business, and the SAP User Experience strategy. |
| Process Orders in SAP S/4HANA < 8% | Characterize process order elements and process order processing, determine master data objects for process orders, identify features for Good Manufacturing Practices (GMP). |
| Material Requirements Planning in SAP S/4HANA 8% - 12% | Select and apply planning strategies, use the planning table, characterize long-term planning and master production scheduling, outline MRP basics and steps of MRP, and describe lot size procedures. |
| Master Data in SAP S/4HANA > 12% | Identify and explain production relevant master data, including, but not limited to: bill of material, routing and production version. |
| Introduction to SAP S/4HANA Production Planning < 8% | Outline production planning components and functions, differentiate consumption-based planning vs. MRP, outline new trends in production planning. |
| Advanced Planning in SAP S/4HANA > 12% | Outline the basics and master data of advanced planning, explain tools (alert monitor, detailed scheduling planning board) and advanced planning and detailed scheduling processes, explain planning evaluation concepts |
Ultimate Guide to Prepare C_TS422_1909 Certification Exam for SAP Certified Application Associate: https://freedownload.prep4sures.top/C_TS422_1909-real-sheets.html